Iran Rail spike anchoring mortar for railway Concrete Project - CT-10
1:Rapid hardening , high strength, micro-expansion , cold construction operation ., 2:Environmental pollution - details see: https://www.buildingsupplieshub.com/iran-rail-spike-anchoring-mortar-for-railway-concrete-project-10089012
Place of Origin: Shandong China (Mainland) | Brand Name: CaiTong | Model Number: CT-10 |
Iran Rail spike anchoring mortar for railway Concrete Project
Description:
The product is inorganic mixture, fast harden\ High intensity \ micro-expansion, Environment-friendly. do not need to warm up in normal condition (20°C\68°F \ 70 % Humidity). Mixed with water is available. Avoid crack due to partial warmed, which reduce the working time of rail spike. Constriction at -10°C\ 14F is available. Well performance after 2 million times destructive test
Applications:
1, It can be used in railway: rail spike anchoring of the concrete railroad crosstie \ crosstie of bridge. It can be used in anchoring of installed bridge bonded joined and the foundation bolt of instrument.
2, It can be used in railway\ tunnel \ channel \ coal mine \ Strengthen of bridge pier \ anti-crack of house \ Metallurgic mine etc. fast construction for anchorage of underground construction with anchoring component. In order prevent stone drop.
3.It can be used in the Strengthen of the concrete construction with reinforcing steel bar. And satisfy the weld of the reinforcing steel bar.
Specifications:
Vertical Expansion Rate (%) | Compressive Strength(M pa) | Rail spike pull-out resistance(KN) | ||
4 hours | 1 day | 3 days | ||
≥0.02 | >20 | >35 | >50 | >60 |
Standard : TB/T2093-2002
How to Use?
No. | Steps | Tools | Requirements of Construction | Remarks |
1 | Take out the old rail spike | special tools | 1. take out the old spike 2. Cleaning the hole of the rail spike. | It’s better to wet the hole with water |
2 | Set the shelf of anchorage | stick | put the shelf of anchorage into the hole | |
3 | Mixing | Container\ spoon\ bucket | Mix 14-16% water with the anchoring agent, mix evenly | Add or reduce water according to situation |
4 | Grouting | spoon | Grouting the mixed anchoring agent into the hole from the middle of the shelf of anchorage. 2cm to the top of the hole it’s better. | |
5 | Put the rail spike | Put the spike after grouting, make sure it’s vertical. | Make sure no oil stain on the spike | |
6 | clean up | Stick | Remove the overflow material | Grouting again if the hole can not full enough |
7 | Fix the fastener | T- spanner | After anchoring (60 min), fix the fastener, screw down the nut with hand, after 120 min screw down the nut with T-spanner, 24hour screw down tightly as required | |
8 | Change the new railroad | It will be available after 1 day curing. | It’s better to spray water after 1-3 days curing |
Notices: dosage of each rail spike ±0.4 kg.
Picture:
Packaging Detail:20kg/bags, 25kg/bags |
Delivery Detail:7-12 working days |